Consultation on Proposed Highway Improvement Proposals:
hUse the following link to find out more https://letstalkcountydurham.co.uk/en-GB/projects/toft-hill-improvements
See below the Consultation Outcomes recently posted on Durham County Council's LetsTalk website page.
The consultation on a package of local transport and highway improvements ran between 10 August and 8 September 2026 and was available online through the Let’s Talk Durham platform, paper copies were posted to 1,300 residents and flyers were made available locally with a QR code linking to the online survey.
The consultation pack posted to residents included a;
(a) letter detailing the proposals with a QR code linking to the online survey
(b) paper survey with return envelope
(c) plan of the proposed schemes
(d) flyer.
The consultation generated a strong level of engagement from local residents and stakeholders, with 254 surveys returned in total.
The majority of responses were from residents of Toft Hill (145 responses, 57%) and High Etherley (74 responses, 29%), demonstrating strong local representation.
The majority of responses were paper based (72 online: 182 paper).
Driving and walking formed the main share of current travel choices with 75% of respondents driving every day for local journeys and 50% of respondents walking in the area every day compared to 1.7% cycling and 1.3% using public transport.
Overall Support for the Improvement Package
Overall support was positive, with 166 respondents (65%) supporting or strongly supporting the package of highway improvements. However, many respondents stressed that the proposals do not address wider concerns regarding traffic volume and HGV movements through the village.
Strong Support for the School Crossing
The proposed puffin crossing outside Toft Hill Primary School received strong support.
Strong Support for Southfield Drive Junction Improvements
The Southfield Drive/A68 junction proposals also received clear support.
Mixed Views on The Three Tuns Parking Improvements
Support for parking improvements near The Three Tuns was mixed.
Change to Junction Priority
A change to junction priority at the Church Street / A68 junction was considered at the design optioneering stage. However, as the proposal was not supported locally or with key stakeholders and sufficient benefits could not identified, it was not included in the consultation. This has been omitted from further investigation and will not be taken further in this package of measures.
Support for Additional Measures
Of the remaining proposals, support was strongest (ranking from the top as the most support) for:
Vehicle Activated Speed (VAS) Signs
Renewal of Road Markings
Improved Bus Shelters
Relocation of Street Furniture
Next Steps
A report, with the consultation results and proposed next steps, is currently being prepared to be presented to Cabinet in December 2026.
The Parish Council’s Position
The Parish Council finds the County Council's current road safety proposals to be seriously lacking, and believes they fall far short of the measures required to ensure community safety.
Consequently, we have submitted a formal consultation response detailing the essential safety measures necessary to safeguard our community and improve the quality of life for our residents.
You can find the Parish Council’s full response here: Read the Parish Council’s full response